Reference
|
Mitigation Measures
|
Status
|
|
|
Water Quality
|
|
|
EIA Report 5.11.2
|
- The lake shall be lined with
an impermeable liner. However, as such liners may have a limited
life span, beyond which the performance may deteriorates, the liner
shall be replaced once the manufacturer’s specified lifespan is reached.
|
Ö
|
|
EIA Report 5.11.2
|
- Stormwater run-off from
surrounding hillsides shall pass through silt traps prior to entering
the artificial lake to prevent siltation. The silt traps shall be
designed to have adequate capacity to retain any silt/sediment contained
within the stormwater. The silt traps shall be frequently
maintained/cleaned to prevent a deterioration in performance.
|
Ö
|
|
EIA Report 5.11.2, EP 3.7
|
- Should the quality of the
water in the Tai Lam Chung Reservoir deteriorate below the present
levels an alternate supply of water, of a quality at least as good as
that within the Tai Lam Chung Reservoir, shall be used to ‘top up’ the
water within the lake.
|
N/A
|
|
EIA Report 5.11.2, EP 3.8, 3.9
|
- If it becomes necessary to
add an algicide to the lake to control algal growth, the algicide shall
be biodegradable with a short half life of
three days or less. During use of the algicide discharge of the
lake water to the marine waters shall be prohibited, until the algicide
has decayed. The algicide shall not be used during periods of heavy
rainfall when overflow of the lake is possible.
|
N/A
|
|
EIA Report 5.11.2, EP 3.6
|
- Stormwater from any
urban/developed areas shall not be allowed to enter the lake as they may
contain pollutants. Sewage effluent from the water recreation
centre shall be transported to the sewerage mains for conveyance to the
Siu Ho Wan STW.
|
Ö
|
|
EIA Report 5.11.2, EP 3.10
|
- Any fuel for motorised water
sports vessels shall be stored in bunded areas, of at least 110%
capacity of the largest fuel storage container to prevent any accidental
spills entering the lake.
|
N/A
|
|
EIA Report 5.11.2
|
- Servicing of any water sports
vessels shall be undertaken at suitable facilities away from the
artificial lake. In the event that fuel or other petroleum
products enter the lake, a suitable clean-up plan shall be
implemented. The clean-up plan being devised by the operators of
the water recreation centre and approved by EPD prior to the
commencement of operations at the water sports centre.
|
Ö
|
|
|
Waste
|
|
|
EIA Report 5.11.2
|
- To minimise the potential
adverse impacts to aesthetics and odour impacts, the HKITP should
maintain floating refuse collection initiatives at both the coast of the
Theme Park and within the artificial lake of the Water Recreation
Centre.
|
Ö
|