4.1
Environmental monitoring was performed between 16 December
2005 and 15 January 2006. All monitoring results in the reporting period were
checked and reviewed.
4.2
All water quality measurements in the reporting period
were below the Action and Limit (AL) Levels.
4.3
Environmental mitigation measures as recommended
in the EIA report, Operational EM&A Plan and EP-01/097/2001/C were properly
implemented.
4.4
No complaint, summon or prosecution related to
environmental issues was made against the Project in the reporting period.
4.5
The operator of WRC is reminded to continue to implement measures as
recommended in EIA Report and EP.